Judgement reserved on whether An Bord Pleanála breached obligations over Apple data centre plan

Judgement has been reserved at the Supreme Court on an appeal over whether An Bord Pleanála breached its obligations in how it approved the first phase of tech giant Apple’s planned €850m data centre in Co Galway.

Judgement reserved on whether An Bord Pleanála breached obligations over Apple data centre plan

By Ann O'Loughlin

Judgement has been reserved at the Supreme Court on an appeal over whether An Bord Pleanála breached its obligations in how it approved the first phase of tech giant Apple’s planned €850m data centre in Co Galway.

While Apple is not proceeding with the Athenry project, the court’s decision is likely to affect the Board’s consideration of similar data centre developments.

The five judge Supreme Court heard an appeal today by two objectors arising from the High Court’s dismissal of their challenge over how the Board dealt with the company’s proposal.

The appeal was brought by Sinead Fitzpatrick, who lives close to the planned development, and Allan Daly, of Athenry.

The proposed  Athenry project which Apple are no longer proceeding with
The proposed Athenry project which Apple are no longer proceeding with

It was opposed by the Board and the State but Apple was not involved.

The central issue concerns the manner in which the Board was required by law to have regard to the potential expansion of the data centre project from one data hall to the possible construction of a total of eight data halls.

The Supreme Court will also consider whether a point of law arises concerning the application of broad general principles of EU law in particular cases which should be referred to the Court of Justice of the EU.

Michael McDowell SC, for the appellants, argued the Board “radically misapplied” the law in the way it granted permission for the first phase.

The Board cannot permit a “salami style slicing and dicing” of major projects to avoid “hard questions” and a “genuine” environmental impact assessment (EIA) of such projects, particularly the impact of their energy demands, he argued.

Eight data halls would increase the total demand on the national grid by between six and eight per cent but the Board conducted an EIA for just one hall, not eight, he said.

Without assessing whether this was a sustainable development from an energy point of view, the Board inspector took the view employment considerations outweighed whatever doubt exists on the energy front, he said.

The Industrial Development Authority had claimed about 300 construction workers would be engaged and the project would involve total investment of about €850m over the estimated 15 years it would take to build all eight halls.

If jobs are to be weighed against energy issues, there must be an effort to balance out the two but there was no effort here to show how 300 jobs justifies a 6 per cent increase in energy requirements, Mr McDowell argued.

Apple had said the centre would be powered by 100 per cent renewable energy but the inspector had concluded the best that could be secured was average renewability figures over the 15 years, he added.

Nuala Butler SC, for the Board, said it was required “to take into account as far as practicable” the potential build out of the Apple “masterplan” for eight data halls.

The Board took the masterplan into account “on a broad level” but disputed an EIA on the entire masterplan was required, she said.

There was no “deliberate project splitting” and “nothing curious” about how Apple applied for permission. The Board had conducted no EIA on the masterplan because it was not granting consent for the masterplan, she said.

All eight data halls were not intended to come on stream until some time between 2030-35 and it would have been completely inappropriate for the Board to decide in 2015 what was going to happen in 2035.

Energy demands were considered and while Apple could not show it would use 100 per cent renewable energy, that situation but could be different in 2035, she added.

James Connolly SC, for the State, supported the Board’s position and also maintained there was no requirement to carry out an EIA on the entire project.

more courts articles

DUP calls for measures to prevent Northern Ireland from becoming 'magnet' for asylum seekers DUP calls for measures to prevent Northern Ireland from becoming 'magnet' for asylum seekers
UK's Illegal Migration Act should be disapplied in Northern Ireland, judge rules UK's Illegal Migration Act should be disapplied in Northern Ireland, judge rules
Former prisoner given indefinite hospital order for killing Irishman in London Former prisoner given indefinite hospital order for killing Irishman in London

More in this section

Joe Biden Biden increases tariffs on Chinese imports of electric cars and chips
Construction - digger working at building site on sunny day Large investment funds eye office and data centre projects now interest rates are about to turn
Housing and renewable energy remain key focus for Cork businesses amid election season Housing and renewable energy remain key focus for Cork businesses amid election season
IE logo
Devices


UNLIMITED ACCESS TO THE IRISH EXAMINER FOR TEAMS AND ORGANISATIONS
FIND OUT MORE

The Business Hub
Newsletter

News and analysis on business, money and jobs from Munster and beyond by our expert team of business writers.

Sign up
ie logo
Puzzles Logo

Play digital puzzles like crosswords, sudoku and a variety of word games including the popular Word Wheel

Lunchtime News
Newsletter

Keep up with the stories of the day with our lunchtime news wrap.

Sign up
Cookie Policy Privacy Policy Brand Safety FAQ Help Contact Us Terms and Conditions

© Examiner Echo Group Limited